USU EASTERN MISCELLANEOUS PROJECTS – PHASE A

UTAH STATE UNIVERSITY 

UTAH STATE UNIVERSITY
PRICE CAMPUS
MISCELLANEOUS PROJECTS – PHASE A

400 East 400 North
Price, UT 84501

Package A Subcontractor Selection

Owner: Utah State University
Architect: Method Studio
Gramoll Construction Contact: Aaron Nielsen
175 West 1100 North
North Salt Lake, Utah 84054
(801) 295-2341 Phone
(801) 295-2356 Fax

Bids Due: 3:00 PM on July 15, 2019

OVERVIEW

Gramoll Construction has been selected by Utah State University through a Value Based Selection Process as the Construction Manager/General Contractor on the USUE Price Campus Misc. Capital Improvements project. 

Package A consists of three separate projects the Utah State University Eastern campus in Price, Utah.  Subcontractor and Supplier bids are requested on the USUE Price Campus Misc. Projects Package A.

Bids are due to Gramoll Construction by Monday, July 15, 2019 at 3:00 PM. 

The three projects this package consists of are the BDAC Glazing Replacement, the Fire Lane Extension and the MCC Storage Shed Addition.  The details of each of these projects and their associated drawings are included below.  The specifications for all three of these projects in included in the same Specification book.

INDIVIDUAL PRICING PROPOSALS ARE TO BE SUBMITTED EACH PROJECT SEPARATELY.

Gramoll Construction will be on site to do a walkthrough of the project sites on Wednesday, July 10th at 10:00 AM.  Meet outside of the south entrance of the Central Instructional Building (CIB) 400 East 451 North, Price, UT 84501.  Troy North (801-824-5794) with Gramoll Construction will be leading the walkthrough.

Please contact Aaron Nielsen (801-295-2341) with any questions. The last day to submit questions will be on Tuesday July 9th by 3:00 PM. A final Addendum (if needed) will be posted on Thursday July 11th by 12:00 PM.

You can review the projects included in Package B here.

Bunnell-Dmitrich Athletic Center (BDAC) Glazing Replacement

    • Project Description: The BDAC Glazing Replacement project consists of –
      • The removal of all sloped glazing and the installation of new sloped glazing units.
      • The removal of all existing exterior storefront/glazing and entrance systems and the installation of new exterior storefront/glazing and entrance systems including the reinstallation of existing storefront doors and automatic openers.
      • The removal and replacement of select entryway/vestibule and stairway light fixtures with new light fixtures
    • Special Notes:
      • The replacement the sloped glazing and the replacement of all other storefront/glazing and entrances needs to be priced/bid separately
      • The Glazing Contractor may be selected through a Value Based Selection Process (to be clarified by addenda if needed).
    • Bid Documents

To save a copy to your hard drive, right click the link and select “Save Link As…”

Fire Lane Extension

    • Project Description: The Fire Lane Extension project consists of –
      • Saw cutting and removal of select portions of concrete and landscaping.
      • Placement of new 8” reinforced concrete paving.
      • Placement of new footings foundations to shore up existing underground utility tunnel.
      • Patching and repairing Landscaping and Irrigation.
    • Special Notes:
      • The Concrete Paving Contractor may be selected through a Value Based Selection Process (to be clarified by addenda if needed)
    • Bid Documents

To save a copy to your hard drive, right click the link and select “Save Link As…”

McDonald Career Center (MCC) Storage Shed Addition

    • Project Description: The MCC Storage Shed Addition project consists of –
      • Saw cut and removal of existing asphalt paving, the placing of new asphalt pavement and associated base/subbase preparation and earthwork.
      • The construction of a new wood framed extension to the existing storage shed including pre-engineered wood trusses, wood framing, wood sheathing and siding and asphalt shingles.
      • Installation of a new man door and overhead door.
      • Installation of new electrical including power, outlets and lighting and any associated equipment.
    • Bid Documents

To save a copy to your hard drive, right click the link and select “Save Link As…”

To save a copy to your hard drive, right click the link and select “Save Link As…”

BID DOCUMENTS

See individual projects for their respective drawings.

ADDENDA

Addendum No. 1 (10 MB, PDF)

Please contact Aaron Nielsen if you have any questions or concerns regarding this project.

Gramoll Construction on behalf of the Utah State University and Method Studio reserves the right to reject any or all proposals or to waive any formality or technicality in any proposal in the interest of the owner.

 

ABOUT US

Gramoll Construction Company provides clients with the highest quality construction…

TESTIMONIALS

What our clients are saying…

SERVICES

Gramoll Construction is dedicated to providing the best project…

CONTACT US

Get in touch with Gramoll Construction…