CURRENTLY BIDDING
- Biology Building Fume Hood Upgrade
- Westlake Emergency Center FSER
- Layton Fire Station 54
- Utah Fertility Center Outpatient Surgery Facility
Biology Building Fume Hood Upgrade
Gramoll Construction has been selected as CM/GC for the University of Utah Biology Building (BLDG 84) Fume Hood Upgrade Phase 1. The project is the upgrade for 8 (7 new replacement, 1 re-used) Fume Hoods, controls, ducting, and replacement of roof top exhaust fans. The work is limited to the North West quadrant of the building. Phases 2, 3, & 4 with similar scope will be procured in the near future as funding becomes available.
Commercial Mechanical has been contracted for this phase for the Mechanical Scope. Gramoll is requesting bids for the remaining scopes of the project including, Structural Platform, Acoustical Sound Panels, Roofing Repairs, Minor Fire Sprinkler Adjustments, Electrical, and Acoustical Panel Ceilings (removal; reinstallation; and new) as shown in the contract documents. Work will need to be phased within the project boundaries with schedule limited to 4 days for office spaces (areas without Fume Hoods) and 10 calendar days for Lab Spaces (Areas with Fume Hoods). All subcontractors will need to work closely with CM/GC and other subcontractors to complete the work within the time frames allowed. Only two areas will be worked on concurrently. Overtime, Shift Work, and/or Night Work will likely be required.
Bids are due to Gramoll Construction by 11:00 AM on Tuesday, April 27. Base Bid Scope is all work shown in Lab Spaces, Alternate #1 is all work in Office Spaces as identified in bid documents.

Owner

Designer

Bids Due
TALK TO US ABOUT THIS PROJECT
Do you have a question to ask us? We have answers that can help.
Gramoll Construction Contact
Mike MacFarlane
155 South 750 West, North Salt Lake, Utah 84054
Phone (801) 295-2341
Fax (801) 295-2356
Cell (801) 949-7442
Bid Documents
Addenda
Check back later.
Westlake Emergency Center FSER
Gramoll Construction is bidding on the Westlake Emergency Center FSER project in Lehi.
The project consists of the construction of a single-story free-standing emergency room (FSER) of approximately 11,070 SF. It contains a lab, pharmacy resuscitation (trauma) room, exam rooms, imaging, offices and associated support spaces. The exterior consists of stone, metal panels and EIFS. Emergency and ambulance canopies are to be constructed as well as a generator and dumpster enclosure and both an underground reclaim and propane tank. The site includes excavation, utilities, curb & gutter, paving, landscaping, and interior and exterior signage. Construction is anticipated to start on 7/1/21.

Owner

Architect

Bids Due
TALK TO US ABOUT THIS PROJECT
Do you have a question to ask us? We have answers that can help.
Gramoll Construction Contact
Mark Bodell
155 South 750 West, North Salt Lake, Utah 84054
Phone (801) 295-2341
Fax (801) 295-2356
Cell (801) 403-4342
Bid Documents
Drawings – Vol. 1
Drawings – Vol. 2
Specifications
Addenda
Please check back later
Layton Fire Station 54
Gramoll Construction is bidding a new Fire Station for Layton City. The new station has about 10,000 square feet, single story, with new truck bays and living quarters. The site is rough graded already and is a new ground up construction. Site can be accessed with no appointment needed. UDOT is currently using the site for laydown, but will be cleaned up in time to start construction in June.
Gramoll is requesting proposals on Concrete, Rebar fabrication, Masonry, Stonework, Steel Fabrication and Erection, Millwork, Waterproofing, Air Barrier, Metal Roofing, Doors and Frames, Overhead Doors, Glazing, Framing, Drywall, Ceramic Tile, Ceiling Tile, Ceramic Tile, Painting, Flooring, Specialties, Flag Pole, Signage, Appliances, Mechanical, Plumbing, Electrical, Excavation, Site Concrete, Asphalt, Landscape.
Proposals are due to Gramoll Construction by Tuesday, May 4th at 11:00 AM.
SCHEDULE
Last Day to Submit Questions by – TBD
Final Addendum Posted by (If Needed) – TBD
Subcontractor & Supplier Bids due by – 5/4/21 @ 11:00 AM
Project Start Date – TBD
Project Substantial Completion Date – 3/25/22

Owner

Architect

Bids Due
TALK TO US ABOUT THIS PROJECT
Do you have a question to ask us? We have answers that can help.
Gramoll Construction Contact
Mark Bodell
155 South 750 West, North Salt Lake, Utah 84054
Phone (801) 295-2341
Fax (801) 295-2356
Cell (801) 550-1952
Bid Documents
Drawings – Vol. 1
Drawings – Vol. 2
Specifications
Addenda
Please check back later.
Utah Fertility Center Outpatient Surgery Facility
Gramoll Construction is bidding on the Utah Fertility Center Outpatient Surgery Facility project in Pleasant Grove. The project consists of but is not limited to: demolition, renovation and construction of level 1 of a three-story steel structure with brick veneer. Work includes modifications to exterior walls to create a surgical suite with adjacent lab space, associated patient care space and staff support spaces. Additionally, the project will include an enclosed mechanical penthouse to be created in an existing semi-enclosed, covered area on the level 3 roof and modification of the site directly adjacent to level 1 of existing paving and landscaping to accommodate a new structural brick mechanical enclosure, new paving and other work indicated in the Contract Documents.
Site Available for Site Visit – 3/25/21 @ 11:00 AM to 12:00 PM
Last Day to Submit Questions by – 4/26/21 @ 12:00 PM
Final Addendum Posted by (If Needed) – 4/30/21 @ 10:00 AM
Subcontractor and Supplier Bids due by – 5/5/21 @ 10:00 AM
Anticipated Project Start Date – 5/24/21

Owner

Architect

Bids Due
TALK TO US ABOUT THIS PROJECT
Do you have a question to ask us? We have answers that can help.
Gramoll Construction Contact
Mark Bodell
155 South 750 West, North Salt Lake, Utah 84054
Phone (801) 295-2341
Fax (801) 295-2356
Cell (801) 550-1952
Bid Documents
Drawings – Vol. 1
Drawings – Vol. 2
Specifications