Salt Lake Campus Relocation, Utah State University

$3,300,000

Project Budget

Method Studio

Project Architect

30,500 SF

Project Size

Value Based CM/GC

Procurement

September 2017 to January 2018

Duration

Utah State University

Owner

OVERVIEW

The Utah State University Salt Lake Center project consisted of the complete interior demolition and remodel of the old 30,500-square-ft ITT Technical Institute building in Taylorsville to be the new home of USU’s Salt Lake satellite campus. The key to this project was to complete the renovation and have the furniture and all systems ready for classes within a four-month period.

 

The project included a new roof, new electrical service and distribution, new mechanical system, new storefront entry with security proximity card access, and new AV classrooms. The work was completed as scheduled.