https://www.gramoll.com/wp-content/uploads/2019/09/“.png

“The quality of the work by Gramoll and their subcontractors was outstanding and something Gramoll took great pride in.”

-Bill Nehmer, President, Great Dane of Utah, Inc.

 

CURRENTLY BIDDING

Davis Technical College - Welding Building Bid Package #2

Gramoll Construction has been selected by the Davis Technical College, and the Utah DFCM as the as the design build general contractor to design and build the new Welding and Technology Building. The project consists of an approximately 17,000 SF new building, including a welding shop, a classroom, and office space on the Davis Technology campus in Kaysville Utah.

THIS IS A TAX-EXEMPT PROJECT
Gramoll Construction’s subcontractor agreement is posted on our website along with all the other project bid documents. All bidding subcontractors, if selected, must agree to all the terms and conditions of the Gramoll Construction Subcontract Agreement.

Gramoll construction is currently requesting bids for Bid Backage #2 which includes but is not limited to the following trades, Air Barrier, Insulation, Metal Wall Panels, Metal Roofing, Membrane Roofing, Doors Frames & Hardware, Storefront & Glazing, Sectional Overhead Doors, Metal stud Framing, Gypsum Board, Tiling, Walk-off Carpet, Rubber Base, Dry-Erase Board Wallcovering, Painting, Concrete Coatings, Toilet Partitions, Diaper Changing Stations, Mirrors, Grab Bars, Corner Guards, Window Coverings, Fire Suppression, Mechanical (not including Under-Slab Plumbing), Asphalt, Landscaping & Irrigation, and Fences & Gates.
THE FOLLOWING TRADES HAVE ALREADY BEEN SELECTED/CONTRACTED AND ARE NOT BIDDING AT THIS TIME, Earthwork, SWPPP Management, Underground Utilities, Electrical, Under-Slab Plumbing, Building Concrete, Foundation Damp proofing, Site Concrete, Masonry, and Structural & Misc Steel.

Bid Package #1 project documents are also available on our website for reference.
All questions regarding this project must be directed to Aaron Nielsen with Gramoll Construction, at 801-295-2341 (801-651-5156 mobile). Aaron.Nielsen@Gramoll.com.

SCHEDULE
Project Documents Available – 11/18/2024
Last Day for Questions – 12/02/2024 – 12:00 PM
Final Addendum Date (if needed) – 12/05/2024 – 4:00 PM
BID DUE DATE – 12/10/2024 – 10:00 AM
Project Start Date – 09/10/2024
Project Completion Date – 09/16/2025

Owner

Davis Technical College

Architect

CRSA

Bids Due Date

Tuesday, December 10th at 10:00 AM

TALK TO US ABOUT THIS PROJECT

Do you have a question to ask us? We have answers that can help.





    Gramoll Construction Contact

    Aaron Nielsen
    155 South 750 West, North Salt Lake, Utah 84054
    Phone (801) 295-2341
    Cell (801) 651-5156
    Fax (801) 295-2356

    Bid Package 2

    Drawings
    Specifications
    Schedule
    Sample Subcontract Agreement

    Bid Package 1

    Drawings
    Specifications
    Structural Calcs

    University of Utah Physical Medicine and Rehab Clinic Remodel

    Gramoll Construction has been selected by the University of Utah as the Construction Manager/General Contractor for the University of Utah Physical Medicine and Rehab Clinic Remodel. Gramoll is currently bidding Bid Package #2 for about 5,800 sq/ft of space. Please open the drawings and preliminary site plan for access, staging and dumpster location. There is an exterior door on the south area of our remodel that has direct access to a loading dock area that a dumpster or trailer could be placed. There is a couple onsite parking stall we will have fenced off for foreman, but any other workers will need to park offsite and shuttle in. We have already demolished the space (minus a few perimeter walls and the floor slab for underground plumbing). There is a floor demo plan on the structural drawings that needs to be bid. There is also an infill portion with geofoam in the NW corner. Pay attention to the wall call outs that call our for lead line shielding and which walls those are called out on. There is a small classroom (Room 155) that needs to be completed by the first week of January (See schedule). This is to allow students to leave their current classroom, which is where our new X-Ray room is going. This will need to be demolished after they move out to allow for construction of our space to continue. There is also a small exterior gas storage area that will have a chain link gate (with Card Reader) and a 20’ tall chain link fence that will separate the gas storage from the bike racks on the west side. Drawings are currently in the second round of code review, and those drawings should be issued by Friday November 8th for those changes. Submittals will need to be completed in the first 2 weeks after award to avoid any delays in material ordering.


    Gramoll is requesting proposals for Demolition, Concrete, Metal supports for exhaust fan and X-Ray equipment, Millwork, Insulation, Fire/Sound Caulking, Doors/Frames/Hardware, ICU Entrances, Glazing, Framing, Drywall, Lead Line Shielding, Flooring, Ceramic Tile, Ceiling Tile, Painting, Specialties, Curtains, Wall Protection, HVAC, Plumbing, Electrical, Fencing, Fire Sprinklers.


    Onsite walkthroughs can be coordinated with Gramoll Construction. Please e-mail (Dustin Gramoll) or call Dustin Gramoll at (801) 678-5111 with any questions.


    Please submit bids to Dustin Gramoll by November 13th @ 10 AM.


    SCHEDULE
    Last Day to Submit Questions – 11/7/2024
    Final Addenda Posted by (If Needed) – 11/11/2024
    Subcontractor Bids Due – 10:00 AM on 11/13/2024
    Project Start Date – 11/25/2024
    Project Finish Date – 4/18/2025

    Owner

    University of Utah

    Architect

    FFKR

    Bids Due Date

    Wednesday, November 13th at 10:00 AM

    TALK TO US ABOUT THIS PROJECT

    Do you have a question to ask us? We have answers that can help.





      Gramoll Construction Contact

      Dustin Gramoll
      155 South 750 West, North Salt Lake, Utah 84054
      Phone (801) 295-2341
      Cell (801) 678-5111
      Fax (801) 295-2356

      Bid Documents

      Drawings
      Specifications
      Schedule (10/30)
      Site Plan

      Addenda

      Addendum No. 1
      Addendum No. 2

      Have a project of your own? Let’s touch base.